We are glad to inform that during the last July, two massive Brazilian FPSO projects achieved an important milestone. The P-74 and P-76 hulls left the Inhauma yard and were towed to each integration site for the final phase of the projects.

Since the beginning of the Cessão Onerosa (P-74, P-75, P-76 e P-77) and Replicantes (P-66, P-67, P-68, P-69, P-70, P-71) FPSOs, OCEÂNICA has performed several engineering and field activities for these units, such as:

  • Stability analyses and booklets
  • Topside modules load-out engineering and coordination
  • Rigging plans and coordination
  • Weight control and modules weighing
  • Vessel ballasting plans and coordination
  • Motion analyses
  • Tow masters and marine personnel
  • Structural analyses for topsides, hull and auxiliary systems;
  • Towing plans, procedures and simulation for all maneuvers from hull conversion yard to integration sites*
  • Mooring plans, procedures and supervision, among others.

Congratulations to all teams involved on these projects!